NJIT Physical Plant and PSE&G personnel are working around the clock to repair faulty electrical equipment in the GITC building. At this time, if all goes according to schedule, IT service restoration will begin tomorrow morning, Saturday, with the majority of IT services being available by mid-afternoon. Until then, student Gmail, Moodle and iTunes willContinue reading “GITC Electrical Shutdown – Friday June 8 – status update”
Author Archives: Kevin Byron
GITC Electrical Shutdown – Friday June 8 – status update
Due to an unforeseen electrical problem in GITC, there will be a significant delay in restoring full IT services. At this time, the NJIT web site, student Gmail, Moodle and iTunes are available. However, no other services will be available for the remainder of the day today. When there is additional information about when servicesContinue reading “GITC Electrical Shutdown – Friday June 8 – status update”
GITC Electrical Shutdown – Friday June 8 – status update
Moodle is now available again at http://moodle.njit.edu. All technical problems related to the Moodle service interruption have been resolved.
GITC Electrical Shutdown – Friday June 8 – status update
Electrical power in GITC has been turned off as scheduled for utility maintenance. Estimated time for power restoration is 7:00am. Moodle is unavailable due to an unforeseen technical problem. However, the NJIT web site, iTunes and student Gmail are functioning. The next status update will be posted at around 7:00am.
GITC Electrical Shutdown – Friday June 8 – status update
Most services have been shut down at this time. NJIT web site is up in “static” mode, i.e. there will be several “dead links”. Student Gmail is functioning. iTunes has been verified. Moodle is temporarily down and is under investigation. Electricity to GITC will be shut off shortly.
GITC Electrical Shutdown – Friday June 8 – status update
At this time, several services are being shut down as scheduled. These services include high performance computing (HPC) systems (i.e. Kong, Hydra, etc.) and legacy ERP services on Alpha nodes. At 10pm, service shutdowns will continue. Only four services will remain available through the night: the NJIT website, student Gmail, Moodle and iTunes.
GITC Electrical Shutdown – Friday June 8
PSE&G has scheduled an electrical upgrade for the GITC building during the early morning hours of Friday, June 8. The upgrade will require that electrical power in GITC be shut off at about midnight and remain off until about around 7:00 am, significantly affecting campus information services and technology. Additional information about the outage and statusContinue reading “GITC Electrical Shutdown – Friday June 8”
NJIT Library Online Catalog is Now Available
The NJIT Library Online Catalog is now available. (previous post at 9:33AM) The NJIT Library Online Catalog is currently unavailable. This problem is under investigation. Estimated time for service restoration is 11:30AM. Please contact the NJIT Computing Helpdesk at (973)596-2900 for assistance or further information. Thank you for your understanding.
Alpha administrative services delay
Alpha administrative services are delayed this morning due to an unexpected problem during after-hours routine production processing. Services affected include HRS Plus, FRS Plus, SIS Plus and Web for Employees. All services are expected to be available by 10:00AM. Please contact the IST Computing Helpdesk at (973) 596-2900 for additional information or questions. Thank you.
Alpha administrative systems service interruption – update #2
As of 3:45PM today, all services have been fully restored on the Alpha administrative system. Please report any unusual problems immediately to the IST Computing Helpdesk at (973) 596-2900. Thank you.